Earthworks on the Inpatient Building site continues with piling well underway.
Piling is well underway with more than 300, 12m-long pile casings delivered to site so far, about half of the total required. Two 160-tonne cranes are onsite, as is a larger "piling" crane which holds the hammer that drives the piles into the ground.
Concrete foundation work is scheduled to commence early next year.